Project Overview: Build only contract. Acute Civil Engineering provided our client with upfront design advice and estimating services. Acute conducted a variety of intrusive investigation works to establish site conditions and minimise risk for the employer. An order was placed once the optimum solution was agreed. The awarded contract to install new suspended RC slab on driven steel piles capable of accommodating heavy steel turning and processing equipment.

Client: Hawkins Projects
Value: £650k
Weeks: 14
Completion Date: Completed